Business Planning and Budget Committee

The Business Planning and Budget Committee met last Wednesday and approved the recommended fiscal 2019 budgets for the Agency fund as well as the St. Lucie, Stanton, Stanton II and Tri-City projects. The full agenda package is available on the Portal. The next Budget Committee meeting is May 30 at 9 a.m. to review the All-Requirements Project’s proposed fiscal 2019 budget. Contact: Rich Popp

 

Audit and Risk Oversight Committee

The Audit and Risk Oversight Committee met last Thursday and approved: 1) Stanton Units 1 and 2 and Indian River Units A through D audit report for fiscal 2016 and fiscal 2017 billings, and 2) retaining Purvis Gray and Company as FMPA’s exteal auditor for fiscal 2018. The full agenda package is available on the Portal. Contact: Liyuan Woerner

 

Board of Directors

FMPA’s Board of Directors met last Thursday and approved: 1) second reading of Ordinance 18-1, which effectuates a change to the exiting Risk Management Investment Policy, 2) the revised Investment Risk Management Policy, 3) fiscal 2018 budget amendment for the Stanton Project, 4) fiscal 2018 budget amendment for the Stanton II Project, 5) fiscal 2018 budget amendment for the Tri-City Project, and 6) the establishment of a Florida Municipal Solar Project Committee. The full agenda package is available on the Portal. Contact: Jacob Williams

 

Executive Committee

The ARP Executive Committee met last Thursday and approved: 1) appointment of Jacob Williams and Richard Montgomery as FMPA representatives to the Public Gas Partners Operating Committees of Gas Supply Pools 1 and 2, 2) the revised Investment Risk Management Policy, and 3) the establishment of an ARP Solar Participants Advisory Committee. The full agenda package is available on the Portal. Contact: Jacob Williams

 

Member Services

Sharon Smeenk’s last day as FMPA’s member services manager was last Thursday. While the department is in transition, members may contact Mark McCain, Mike McCleary or Sharon Samuels with any member service needs.

 

Plant Managers Meeting

Managers from Cane Island Power Park, Stock Island Generating Facility and Treasure Coast Energy Center met with FMPA’s power resources staff in Orlando last week. The group discussed plant safety, recent outages, lessons learned, and sharing of resources for increased reliability and cost savings. Contact: David Schumann

 

Grant Opportunities
Sharon Samuelsemailed a list of potential grant opportunities last Monday to interested FMPA members. The Member Services Department has a subscription to Grantfinder.com to assist members in identifying potential funding sources. The service was purchased after several members requested assistance with grants and the service options were discussed with the Member Services Advisory Committee. Member Services is sending out periodic emails with grant opportunities. If you would like to receive the emails, contactSharon Samuels.

 

Promotion

Congratulations to Brandon McCormick, who was promoted last week to Regulatory Compliance Program Manager.

 

____________________________________________________

 

THIS WEEK

 

Hurricane Tabletop Exercise

FMPA and staff at FMPA’s power plants will participate in a tabletop exercise Monday to assess the preparation, response and restoration plans for a hurricane. During the exercise, staff will discuss a storm scenario and individual roles and responsibilities. Contact: Frank Gaffney

 

Stock Island Upgrade

Carter Manucy will be in Key West this week to upgrade computers that control Stock Island Units 1, 2 and 3. He will also provide training for power plant operators.

 

Member City Visits

Chris Gowder and Navid Nowakhtar travel to Homestead on Tuesday to meet with Barbara Quiñones, director of utilities, and William Branch, assistant director. They will discuss load forecasting, power supply and the value of municipal utilities. Jacob Williams will travel to Key West on Wednesday to meet with KEYS General Manager and CEO Lynne Tejeda and staff members at the Stock Island Generating Facility, including new plant manager Joe Weldon.

 

All-Requirements Project Weekly Load Statistics

The weekly update of the All-Requirements Project historical load graph has been posted on the Portal. The graph is updated through May 20. Contact: Jim Atz

 

____________________________________________________

 

COMING UP

 

Memorial Day Holiday

FMPA’s offices will be closed May 28 in observance of Memorial Day. Have a safe and happy holiday.

 

Crew Leadership Course

FMPA will host a two-day Crew Leadership Course presented by Northwest Lineman College at FMPA’s Orlando office June 6-7. The training provides crew leaders and general foremen with the knowledge and tools to lead crews efficiently, responsibly and safely. Registration costs $650 per person and breakfast and lunch are included. FMPA will invoice participants for the course. Contact: Sharon Samuels

 

System Control Roundtable

FMPA will hold a System Control Roundtable on July 11 at 10 a.m. in Lakeland. The roundtable will be an opportunity for operators of power generating units to discuss common issues, share best practices and network with fellow member utilities. The program is targeted to system control personnel who are involved with daily system switching, trouble call dispatch and facilitate crew locations and field activities. There is no cost to attend, and lunch will be provided. Registration is available on FMPA.com. Contact: Mike McCleary

 

FMEA Annual Conference

Registration is open for the Florida Municipal Electric Association’s (FMEA) Annual Conference scheduled for July 17-19 at The Breakers in West Palm Beach. The conference includes the annual FMPA Board of Directors luncheon and other FMPA governing board meetings.

____________________________________________________

 

INDUSTRY NEWS

 

FPL Agrees to Refund Hurricane Charges

Florida Power & Light (FPL) reached an agreement last week with the Office of Public Counsel to refund $27.7 million to customers that the utility over-collected to cover the cost of recovering from Hurricane Matthew in 2016. The agreement must be approved by the Florida Public Service Commission. If approved, residential customers who use 1,000 kWh a month would receive a one-time bill credit of $3.18.

 

PSC Accepting Applications

The Florida Public Service Commission (PSC) began accepting applications last week for two seats on the commission that are scheduled to open in January when the terms of Commissioners Julie Brown and Gary Clark expire. The PSC’s nominating council set a deadline of June 12 for applications. Commissioners on the utility regulatory board are appointed by the govenor and earn $132,036 per year.

 

____________________________________________________

 

FMPA Weekly is published by FMPA for employees and goveing boards of FMPA member utilities. Questions or comments about this newsletter may be directed to Jeff Grainger in FMPA’s Public Relations Department.

 

Want more background on the names and terms used in this newsletter? Check out FMPA’s Glossary, which features some of the most frequently mentioned committees, companies, places and terms, or contact the person named in each FMPA story to lea more.

 

Have a question, comment or story idea for the newsletter? FMPA welcomes your feedback at any time. Contact: Jeff Grainger